What a loan costs you is not the interest rate and not the amount you borrow. It is what you repay minus the cash that actually reaches you. Fees taken from the loan count twice: you pay them, and they shrink the money you get to use.
Take a ₱5,000 loan over two months at 5% a month, with ₱350 in fees taken when the loan is released. You receive ₱4,650 and repay ₱5,378.05. The interest is ₱378.05, but the loan costs you ₱728.05.
To find that number on any offer, look for three lines of the Loan Disclosure Statement: the amount borrowed, the net proceeds and the total of the payment schedule.
Three amounts that decide the cost
| Amount | Where to find it | What it means |
|---|---|---|
| Amount borrowed | Line 1, Loan granted | The loan on paper; interest is usually worked out on it |
| Net proceeds | Line 7 | The cash released to you: line 1 minus the fees in line 5 |
| Total you repay | Line 11, payment schedule | Every payment you will make, added up |
Lending and financing companies that lend through an app or website must show you these amounts, the rates and every fee before you confirm the loan, under SEC Memorandum Circular No. 20, series of 2026. The money may not be released until you confirm.
A ₱5,000 loan, line by line
Here is an illustrative statement for ₱5,000 repaid in two monthly payments. Interest is 5% a month on the balance still owed, and the lender takes a ₱250 processing fee and a ₱100 service fee from the loan.
| Line | Amount |
|---|---|
| 1. Loan granted | ₱5,000.00 |
| 4a. Nominal interest rate | 5% a month |
| 5a. Processing fee | ₱250.00 |
| 5f. Other charges (service fee) | ₱100.00 |
| 5g. Total non-finance charges | ₱350.00 |
| 7. Net proceeds (line 1 minus line 5) | ₱4,650.00 |
| 9. Effective monthly interest rate | 10.27% |
| 11. Total of the payment schedule | ₱5,378.05 |
The payment schedule shows where the interest comes from. Each month the lender charges 5% on what you still owe:
| Payment | Amount | Interest | Principal | Balance after |
|---|---|---|---|---|
| Month 1 | ₱2,689.02 | ₱250.00 | ₱2,439.02 | ₱2,560.98 |
| Month 2 | ₱2,689.03 | ₱128.05 | ₱2,560.98 | ₱0.00 |
| Total | ₱5,378.05 | ₱378.05 | ₱5,000.00 | — |
Notice the first month: interest is 5% of ₱5,000, the full loan, even though ₱350 of it never reached you. You pay interest on the fees too.
Your cost in one subtraction
The same ₱728.05 splits into ₱378.05 of interest and ₱350 of fees. Subtracting from the amount borrowed instead would give ₱378.05 and hide the fees. Subtracting from the cash you receive shows everything.
This is also why the effective rate, 10.27% a month, is about twice the 5% in the contract. The effective interest rate (EIR) measures interest and fees against the cash you get, so it is the number to compare between offers.
Read line 7 before you confirm. If the cash you will receive is much lower than the loan, the fees are doing more of the work than the interest rate.Fees taken from your loan
Processing, service, notarial, verification and similar fees are allowed, but they must be in the statement before you confirm. For unsecured, general-purpose loans of up to ₱10,000 with a term of up to four months, SEC Memorandum Circular No. 14, series of 2025 adds two limits that include these fees:
- the effective rate, interest plus all fees, may not go above 12% a month;
- interest, fees and penalties together may not go above 100% of the amount borrowed.
The example stays inside both: 10.27% a month, and ₱728.05 against a ₱5,000 limit. A fee that appears for the first time after you confirm, or a deduction that is not in line 5, is not part of the deal you agreed to.
If you pay late
Late payment fees are not in the EIR and not in the total of the schedule. They have their own line, line 8, usually a percentage of the overdue amount.
For the same small loans, the SEC caps penalties at 5% a month on the overdue scheduled amount. If the second payment of ₱2,689.03 were a month late, the penalty could be at most ₱134.45 for that month. And the 100% cap still holds: interest, fees and penalties together may never pass ₱5,000 on this loan, however long the delay.
Paying late still costs you, and it can show up in your credit history. If you see a due date you cannot meet, talk to the lender before the date, not after.
If you want to pay early
Line 4c of the statement is the pre-termination fee: what you pay to close the loan before the end of the term. Under the Financial Products and Services Consumer Protection Act, the lender must tell you the cost of paying early before you sign. Check this line if you expect money before the last due date. With interest charged on the balance, paying early usually saves the interest of the remaining months, minus any pre-termination fee.
When the cash does not match
The amount that reaches your e-wallet or bank account should be the net proceeds on line 7. If it is lower, ask the lender to explain the difference in writing. The bottom of the statement lists the company’s complaints desk email and hotline.
Hello. My loan [loan reference] was released on [date]. The Loan Disclosure Statement shows net proceeds of ₱[amount on line 7], but I received ₱[amount received]. Please explain the difference in writing and list every deduction with its amount. Thank you.
Keep a screenshot of the statement you confirmed and of the transfer you received. If the lender does not answer or does not fix the difference, you can bring the complaint to the SEC, which supervises lending and financing companies.
Questions
Why did I receive less than the loan amount?
Because the lender took its fees from the loan. The amount you should receive is the net proceeds on line 7 of the Loan Disclosure Statement.
Do I pay interest on the fees?
Usually yes: interest is worked out on the loan granted, line 1, which includes the fees kept by the lender. That is one reason the effective rate is higher than the contract rate.
Is the total I repay minus the amount I borrowed the real cost?
No. That gives only the interest. Subtract the cash you actually received to see interest and fees together.
Are processing fees legal?
Yes, if they are disclosed before you confirm. For loans up to ₱10,000 and up to four months, they count toward the 12% monthly EIR ceiling and the 100% total cost cap.
Prepared by the Zoralytics editorial team. Examples are illustrative and are not offers from any company. This guide works through one illustrative loan; it does not check your own contract. Your numbers are in your Loan Disclosure Statement and payment schedule.